Design Audit Requirements
DRAWINGS (CLOSE TO WHAT INSTALL DRAWINGS WOULD BE)
a) PDF VERSIONS OF:
i) ¼” OR ½” SCALE DRAWING
ii) PLAN – NEW AND EXISTING IF RECONFIGURE
iii) ELECTRICAL PLAN
iv) PANEL PLAN WITH TEXT / PANEL TYPES
v) COMPONENT PLAN WITH TEXT
vi) ELEVATIONS – PANELS AND OFFICES IF MOUNTING OVERHEADS/TACKBOARDS
(1) DIMENSIONS ON FLOOR TO OVERHEADS, TACKBOARDS, WORKSURFACES & OVERALL
vii) PANEL TYPE TEXT IS ON
viii) RENDERINGS IF APPLICABLE TO PANEL CONFIGURATION/TILES
FINAL PLANS/DRAWINGS
BOM –
a) SUBMITTED AS A CAP SHEET UNDER THE SKG TEMPLATE
i) HEADER & FOOTER ENTERED
b) AFTER DESIGNER HAS DONE 1ST CHECK
c) ALL LINES FROM SSS HAVE BEEN ADDED AND BOM IS COMPLETE
PREVIOUS ORDER IF MATCHING FINISHES OR RECONFIGURE
FINAL SIGNED OR VERBAL APPROVAL VISUAL FROM CLIENT/SSS
ALL VENDOR QUOTES FROM SSS
ANY ADDED INFORMATION YOU THINK WOULD BE USEFUL IN THE AUDIT PROCESS
Specials Reviewed
SSS / SALES WILL SELF AUDIT IF:
DESIGN WAS NOT INVOLVED IN THE DRAWINGS AND SPECS FOR THE PROJECT
****3RD PARTY STANDARDS REQUIRED****
DESIGN MANAGER TO BE AWARE OF UPCOMING LARGE PROJECTS NEEDING AN AUDIT
INVITE DESIGN MANAGER TO AUDIT DOWNLOAD MEETING WITH 3RD PARTY DESIGNER AND SKG TEAM
FOR PROJECTS LARGER THAN $100K.
3RD PARTY DESIGNER TO EMAIL SHARE DRIVE FOLDER WITH FOLLOWING ITEMS:
a) FINAL/CURRENT CET PLAN
b) ACAD BASE PLANS FROM ARCHITECT
c) BUDGET BOM
SSS/SALES PROVIDES:
a) BUDGET BOM IF THE BOM FROM THE DESIGNER HAS BEEN ALTERED
b) SIGNED OR APPROVED CLIENT VISUAL
c) REQUEST DESIGN AUDIT THROUGH SMARTSHEET TO DESIGN MANAGER FOR AUDIT
d) VENDOR QUOTES / SPECIALS
TRANSFER OF FILES TO R DRIVE:
ANY AND ALL FILES ONCE PRODUCT IS ORDERED FROM SO# WILL BE TRANSFERRED TO DESIGN BY:
a. SALES ‐ THROUGH S DRIVE FOLDER PATH RECEIVED FROM 3RD PARTY.
OR
b. 3RD PARTY DESIGN TO SEND A LINK FOR ALL DOCUMENTATION/DRAWINGS TO DESIGN
MANAGER IN SKG STANDARD FORMAT