Crane Plan Review Request Form

This form must be completed by a project manager and submitted 14 business days prior to any mobile crane use on campus. Please allow EHS up to 3 business days for review and refer to the following EHS reference guide for more information prior to submitting your request.


Mobile Crane Use on Campus


The following documents will be required to complete your submission:



  • Crane Plan Review (make and model of crane, lift capacity, boom angles musts be listed, annual and quad testing certification dates)
  • Job Hazard Analysis (hazards identified + mitigating activities)
  • Crane Operator / Rigger / Signalman Certification Cards (Type of crane and expiry date musts be clearly listed)
  • Current Medical Examiner’s Certification for Crane Operator
  • Traffic Control Plan (Map of crane transport route)