Crane Plan Review Request Form
This form must be completed by a project manager and submitted 14 business days prior to any mobile crane use on campus. Please allow EHS up to 3 business days for review and refer to the following EHS reference guide for more information prior to submitting your request.
The following documents will be required to complete your submission:
- Crane Plan Review (make and model of crane, lift capacity, boom angles musts be listed, annual and quad testing certification dates)
- Job Hazard Analysis (hazards identified + mitigating activities)
- Crane Operator / Rigger / Signalman Certification Cards (Type of crane and expiry date musts be clearly listed)
- Current Medical Examiner’s Certification for Crane Operator
- Traffic Control Plan (Map of crane transport route)