OPPD Development Request Form

Please enter the project name followed by location.

Example: New Apartments (123 Main St)

Select or enter value
Caret IconCaret symbol

Project Manager/Engineer Details

Select or enter value
Caret IconCaret symbol

SID Details


Developer Details


Project Details

Streetlights*
Select Project Type:*
  • A form will need to be filled out for each project type

Please note an attached preliminary plat is required.

AutoCAD & PDF Please Attach Below in File Upload

Paving plans

PDF Only

Grading Plans

PDF Only

Sewer Plans

PDF Only

Water Plans

PDF Only

Landscaping Plans

PDF Only

Non-Residential Electrical Loads and Voltage

(Wells, Lift Stations, etc.) - PDF Only

Connected Electrical Loads and Voltage

(Elevators, mixed-commercial uses, etc.) - PDF Only

All Electrical Plans

This should include one-line showing main and feeder schedule.

Drag and drop files here or

NOTE: PDF of all plans and AutoCAD file of Final Site Plan or Plat are REQUIRED for completion of OPPD design and metering specifications.


NOTE: A complete OPPD design may take 6-8 weeks from the date all plans are received, or an additional 4-6 weeks if any sets of plans are modified that significantly impact OPPD’s final design.

Construction Schedule

Please enter estimated dates for the start of grading, sewer, paving, water, and gas.


Site Readiness

Grade:


• No steeper than 6:1 at equipment locations including applicable clearance requirements.


• If this criterion cannot be met additional easement shall be granted.


Trees:


• All trees within dedications along the cable path must be completely removed (roots graded out as well); or grant additional easements.


In Service Date:


• Developer/Developers Engineer shall provide a suitable “in service date” to ensure OPPD operations appropriately plans/executes installation according to developer’s needs.


• Developer understands that OPPD will not provide a day to day on site arrival and work time frame. Utility Coordinator shall share week block time work schedules (crews may be working in the URD at any time, but we will not provide daily or hourly updates)


Ducted Residential Service Reminders

Meter


M-1 200-amp - height must be 30" min. to 48" max. from ground line to bottom of meter socket.


M-2 320-amp: height must be 30” min. to 42” max. from ground line to bottom of meter socket


M-3 OPPD riser/cable uses knockout on opposite side from the service to home. Note: 320-amp sockets must only use bottom left knockout.


Riser


R-1 Schedule #80 PVC riser from ground line to socket.


R-2 Must be straight vertical run and flush with outside wall.


R-3 Expansion/slip riser set for maximum expansion, over two inches will result in turndown.


Duct


D1 Developer has copy of the pedestal each lot is designed to be fed from, which is where the stub out is installed. Going to the incorrect pedestal will result in a turndown.


D2 Duct depth 30” min. to 54” max. (duct installed shallow or too deep will be turned down)


D3 Customers using 2 ½ duct must supply a 3” to 2 ½ reducing coupling.


D4 No more than one 90-degree bend will be allowed in a service, if it doesn’t pull, will be turned down.


D5 If duct is not completed to the pedestal/transformer, please do not sod the area until OPPD has completed excavation.


D6 If OPPD needs to complete duct into pedestal/transformer, please do not grade out utility locate marks.


D7 If duct is not connected to a stub out or all the way into the OPPD equipment- contact New Services. This will get the appropriate crew needed to speed up service.


D8 In winter/frost conditions please do not leave the end of the duct pit open to fill with water and freeze, backfill and mark the end.


D9 Cap the end of the duct if not connecting to OPPD stubout.


D10 Bring duct straight to the pedestal, to eliminate as many bends as possible.